Laserfiche WebLink
Mashme Public Libra - PCO/Change Order Loq 10/7/09 <br /> DESCRIPTION Issue Beason For Change Original Final Change <br /> Date 1E Value I Value Class <br /> PCOI Electric primary installation originally by_IVICLP 12123108 MCLP was originally to install and ML to share in 50150 cost, $33,023.60 $23,588,00 Scope <br /> PCO2 C <br /> urbing along Stec ie Street and in entrance drive. 212109 Scheduled to be completed by MCLP.Put pricing together to help them out. 13,153.00 6.00 n/a <br /> CE#1 Structural Steel Modifications 2118109 Elements of structural steel which did not get inco orated in final design. 11,904,00 11,904.00 Design <br /> PC03 Elevator Vent Modificabons 4116109 Credit:Reduced he ig ht of structure which than ges framin g&co p per claddin g -880.00 -1,080,00 Design <br /> PC04 Roof Flashing 4116109 Exploring the option to upgrade the roofing flashin s from aluminum to coeper. 4,903.50 5,477.00 Upgrade <br /> P5 Recessed TV Cabinet 4129109 Provide a recessed area in the millwork to accommodate a new informational screen. • 0.00 0,00 Upgrade <br /> PC06 Asphalt Shingles Prevision 4129109 Upgrade roofing stem to accommodate 120 MpkYond rabri . 9,758.79 10,902.00 Design <br /> PC07 Window Treatment Revisions 6112109 Credit:Eliminate North facing window shades.Add on South face. 2,500.00 -700.00 Design <br /> Y <br /> _PCOB HVAC Revision 5/13109 Added HVAC suppiy at Building Storage Room 113 1,180.00 1,180.00 Design <br /> PC9 Elevator Electrical Revisions 5113109 Credit:Changes to the main distribution due to reduced elevator r uirements, -95.00 -955.00 Design <br /> PC 10 Site Lighting Revisions 5/19109 Credit:Reduce number of side wally poles on Steeple and chane a at entrance drive. -3,049.00 -8,049.00 Design <br /> PC 11 PV Mounting 5127109 Upgrades required to tie PV supports to roof structure. 18,000.00 12,224.00 Desi n <br /> PC012 Door Hardware Revisions 5127109 Costs associated with rovidin additional doors with security access control. 0.00 5,367.00 Design <br /> CE#8 CAD design time incured by HVAC sub. 8118/09 Time invested by HVAC sub-contractor to coordinate ductwork for G G D. 3,081.00 8,081.00 Design <br /> PC 13 Revisions to ceilin desi n in Children's Area 6124109 JR rep omended simpli_Ning the cell ing system after seeing the product submittals. 0.00 -3,800.00 Design <br /> PCO 14 Provide backflow preventer for boilers. 7!7109 Required by code. 2, 88.07 2,445,00 Design <br /> PCO 15 Electrical floor box revisions in Young Adult Room 7!8109 Revisions as a result of furnishings meetings. -208.81 209.00 Design <br /> CE#15 Lower openings at 2nd floor windows 71.7109 Mis-communication between the Arch and G C that was not documented with an RFI 2,274.00 2,274.00 Design <br /> PCO 16 Door 111 Access Control 815109 Cost associated with providin 9 correct infrastructure at Door 111 800.00 0.00 Desi2r <br /> PCO 17 PV Inverters Disconnects 8110109 N STAR req wires extehor discon nett switches located next to meter for each inverter 1,788.00 1,788.00 Design <br /> PCO 18 Induction units at 202&207 8118109 Splitting one unit into two will allow ceiling heights to remain as shown in drawings 9,238.00 0.00 Design <br /> CE#21 Added baby changing station 8110/09 Plans call for"5y Owned'.Asked G C for rice to keep cons istant with other 28b.00 285.00 Scope <br /> CE#22 Disconnect switches at chiller 9116/09 Specified chiller was submitted with single point connection,chiller on site has two point connection 1,000.00 0.00 OC <br /> CE#23 Relocation of FA Cabinet,pull station,&strobe 8112109 heeded to be done to clear the donor walls ace.T&M 500.00 874.00 URRrade <br /> _PC0 19 Provide widna for hand driers in bathrooms. 8/20109 Requested by Town to upgrade from hand towels to driers. 1,500.00 4,588.00 Upgrade <br /> PCO 21 Second floor water cooler 9114105 "Chiller"component of ori final water cooler would not fit due to a cross brace OM 2,157.00 Design <br /> PCO 22 Tile at donor wall 9/16/09 Decided during desi n phase of donor wall 0.00 0.00 Design <br /> CE#26 -Rolling shelving rails. 511109 Needed because room is larger than in the old library storage room. 1,100.00 1,319.00 Upgrade <br /> PCO 20 Syppprtsystem for precast panels at entrance. 8119/09 Issue between Arch-and Filed-sub as to res ponsibiIi .RP s 99 a ted 50150 to move on. 5,000.00 0.00 '? <br /> CE#27 Paint b owner 0!17/09 edfiration gall for''Owner"t0 provide exterior trim paint 1,486.00 1,485.00 Smpe <br /> Totals $1111719.45 .$80.825.00 <br /> Totals by Change Class; Comments <br /> Scope $25,358.00 <br /> Non-Scope 0.00 <br /> Design 43,529.00 <br /> Upgrade 112938.00 <br /> Total $80,825.00 <br /> Change Order Recar) Status <br /> co#1 $35,492.00 Approved <br /> CO#2 30,066.00 Approved <br /> CO#3 5,355.00 Approved <br /> CO4 1,821.00 Approved at Pre) <br /> CO#4 8,091.00 Pending approve <br /> Total $80,825.00 <br /> Pomroy Associates-Most Recent Report 9-22-09 <br />