changes, which the architects will have to be compensated for . <br /> Bob explained , in their opinion, 16 months is not enough time to construct <br /> this facility, it needs 18 months, <br /> You cannot complete construction and move in at the same time, <br /> Joe asked if the schedule is slipping? <br /> Bob said it has slipped alread . Ian strongly suggests deferring occupancy <br /> of the building until Jan . 1997 . <br /> Bob agrees Jan, 1997 makes sense. Everyone i s under pressure to male <br /> decision more quickly. <br /> Can the students be allowed to continue at Falmouth for the first Semester? <br /> ? <br /> Merry sue said that i s not an option. <br /> The School committee understands they may have to find other options and <br /> male a decision . This group has to decide if that is going to be the <br /> schedule and inform the School Committee. <br /> The committee agreed to decide next month if the schedule should be <br /> extended to Jan 1997 . <br /> Ian i"s very concerned about the sewage treatment plant- i t a s going no <br /> where. <br /> Bob said Peter did not want to make a decision tonight* <br /> Bob is going to tell Mark Pare to stop work. People in Town feel he is not <br /> working in the best interest of the Committee. There is incompatibility <br /> with the Health Dept. If it is a problem with personalities it will never <br /> be resolved. <br /> They will have to settle the account with Pare and get someone else on as <br /> soon as possible <br /> Tom wren explained that Chartwell was asked to gather the existing data re <br /> flows . Chartwell are not engineers. The Town has someone, like Mark Pare, <br /> who can provide imerpretation on those figures. <br /> Bob said they can ' t start construction without approval from DEP. <br /> Mark Pare has been able to get concessions with DEP because of his personal <br /> relationship with them. He is also able to ask for quick review by DBP when <br /> it is needed . <br /> DePao wait and Pare are the best in the area in designing plants . <br /> The committee suggested asking the Health Department to attend next week's <br /> meeting. As Elias McQuaid what he wants to see (for plant) and can he work <br /> with Mark Pare <br /> Merry sue said she doesn't think this meeting is the place for that <br /> discussion to happen. <br /> Bi 11 said thep roblems need to be resolved , we need to stick with them <br /> because of the time deadline. <br /> Is Mark Pare aware there is a problem? <br /> Bob said he is not., <br /> The committee agreed to ask Elias cQua i d to the next meeting to ask him to <br /> gather the data on flows of other high schools and to talk about sewage <br /> treatment plants. <br /> Friday, sept 23rd there is a meeting at 1 : 30 to talk about the EIS* Joel <br /> Seeley and Brian Lawler will represent SMMA. <br /> 9 <br />