Mashpee Planning and Construction Committee <br /> Minutes of Meeting Held Wednesday, December 1, 2021 <br /> Mashpee Town Hall—Waquoit Meeting Room <br /> Committee Members Present: Joe Brait, Tom O'Neill, Cathy Lewis <br /> Absent: Steve Cook and Rachel Hodgman <br /> Also Present: Catherine Laurent, DPW <br /> Ashley Lopes, School <br /> Vice Chairman Joe Brait called the meeting to order at 5:00 p.m. <br /> Old Business <br /> Update on DNR_Facility <br /> Instead of pursuing a new facility on Red Brook Road,the Town approved funding at the May <br /> 2021 Town Meeting to purchase two units in an existing industrial building on Mercantile Way. <br /> The combined size of the units is 2,400 square feet. Purchase occurred in June 2021. The <br /> services of an architectural firm were engaged to develop construction plans for renovating the <br /> two units. Fifty percent plans were just received. One unit will contain offices, a <br /> conference/break room, locker facilities, and a lab. The second unit will contain offices and one <br /> garage bay for boat/equipment maintenance. The 50% cost estimate received exceeds the <br /> available funding of$225,000. Even if DPW staff were to perform some of the work, additional <br /> funds will be needed. A placeholder is included in the FY23-FY28 CIP being discussed later in <br /> the meeting. Over the next month, DPW will try to finalize the estimate. Quotes have been <br /> requested for work to be contracted including HVAC, plumbing, electrical, fire suppression, and <br /> alarm. The Committee discussed issues with increasing prices and availability of materials and <br /> labor. The estimate should include a high contingency for these reasons. Tom volunteered to <br /> represent the Committee on this project. <br /> Update on FY22-FY27 CIP <br /> This item was deferred to the next meeting. <br /> Update on Phase 1, Mashpee Wastewater Plan <br /> Phase 1 will include construction of a treatment facility on Asher's Path adjacent to the Transfer <br /> Station as well as three pump stations for the collection system. As this time, bidding for <br /> construction is expected in Spring 2022. Catherine will follow up with the Town Engineer on <br /> the schedule and final plans. Joe volunteered to represent the Committee on this project. <br />