Town of Mashpee Sewer Commission <br /> t <br /> 16 Great Neck Road North <br /> Mashpee, MA 02649 <br /> Phase 1 <br /> • April through May 20tn <br /> o Finished Equipment Testing and Training <br /> o All Training is Video Recorded <br /> • Fire Alarm/Suppression System Demonstration for Fire Dept Being Coordinated <br /> Phase 1 Collection System <br /> • Phase 1—Green and Orange Areas (Colors refer to Map in Presentation) <br /> o Communication system in place <br /> o Clearwater test complete for PSs <br /> • Phase 1A— Blue Area (Refers to Map) <br /> o Crews came back to the Brewster Road PS <br /> What is needed for Phase 1 System Activation (Operation) <br /> • WRRF Accepted by DEP <br /> o DEP Clearwater Test— May 20, 2025 <br /> ■ Demonstrate entire plant operation <br /> ■ Equipment functions <br /> ■ Instruments function <br /> ■ Alarms function <br /> ■ Communications function <br /> ■ Safety features' function <br /> Chair Harris asked who comes from DEP—a team or just one person. Mr. Drainville answered <br /> that he has, in the past, had a team and one person. Mr. Meader answered that Aaron from <br /> DEP was the main person at the pump station and two (2) other people. <br /> • Pump Stations Accepted by DEP <br /> o Clearwater Test Completed in April <br /> o Team will demonstrate two (2) items on May 20, 2025, and this test will be <br /> complete. <br /> ■ Successful test is required for DEP approval to accept wastewater <br /> • Collection System Accepted by Town <br /> o RBO (Robert B. Our) requested substantial completion <br /> o Town can issue substantial completion <br /> o Large users ready to hook up <br /> o Town ready to invite customers to hook up <br /> o Wastewater should be seen at the plant by late May <br /> ■ Substantial Completion is required for Town to Activate the Collection <br /> System <br /> Chair Harris asked about the large users that are ready to hook up —whether the permits have <br /> been issued to them or is it just that the structures are there. Mr. Drainville answered that the <br /> infrastructure is in the street and the RBO contractors who have been engaged to tie in, and <br />