QUASNNETELEMENTARYSC1400L Building- Estimate Detail
<br /> Window Replacement&Assoclated Work
<br /> Mashpee,MA
<br /> CONSTRUCTION BUDGET COST REPORT
<br /> September 13,.2016
<br /> Quantity unit Rate Total
<br /> B2010 EXTERIOR WALL
<br /> Miscellaneous
<br /> Allowance 18,655 5F 3.00 55,965
<br /> Subtotal $55,965
<br /> B2020 WINDOWS
<br /> Aluminum windows and glazing
<br /> Aluminum windows,including metal panels and
<br /> incorporated louvers
<br /> North elevation 1,545 SF 100.00 154,500
<br /> South elevation 983 SF 100.00 98,300
<br /> East elevation 565 SF 100.00 56,500
<br /> West elevation 1,213 SF 100.00 121,300
<br /> Courtyard 1 992 SF 100.00 99,200
<br /> Courtyard 2 1,056 SF 100.00 105,600
<br /> Courtyard 3 966 SF 100.00 96,600
<br /> Other systems
<br /> Louvers
<br /> Not part of window system 179 SF -100.00 17,900
<br /> Ancillaries
<br /> Backer rod and double sealant 10,980. LF 6.00 65,880
<br /> Wood blocking at openings . 10,980 LF 5.50 60,390
<br /> Sill flashing 1,427 LF 22.00 3.1,394
<br /> Panning system to windows 5,490 LF 15.00 82,350
<br /> Pvc trim
<br /> Interior sill 1,427 LF 25.00 35,675
<br /> Interior jamb/head trim 4,404 LF .12.00 52,848
<br /> Facing trim 3,834 LF 10.00 38,340
<br /> Paint to trim 9,665 LF 2.50 24,163
<br /> Subtotal $.1,140,940
<br /> r
<br /> 82030 EXTERIOR DOORS
<br /> Hollow metal doors,frame and hardware
<br /> Single leaf
<br /> Complete 2 EA .2,200.00 4,400
<br /> Double leaf
<br /> Complete 7 PR 4,000.00 28,000
<br /> Aluminum doors including transoms and sidelights
<br /> Single leaf
<br /> Complete 10 EA 3,800.00 38,000
<br /> Double leaf
<br /> Complete 7 PR 10,000.00 70,000
<br /> Miscellaneous
<br /> Added cost for door operators 4 EA 4,000.00 16,000
<br /> Paint to door and frame 16 EA 120.00 1,920
<br /> Backer rod and double sealant 26 EA 90.00 2,340
<br /> Wood blocking at openings 26 EA 80.00 2,080
<br /> Subtotal $162,740
<br /> enness�
<br /> ea�sUftlnQ Page 9