Laserfiche WebLink
Project F epresentative' Daily Report Page 1 of <br /> Report No. 29 <br /> Date: 81519 <br /> Architect: strel alovsky& Hoit, Inc. Day: M T W TH F <br /> Project: Mashpee Town Hall Contractor D"Agostino Associates <br /> Superintendent: Len Paoletta <br /> Weather: 8:00 AM SunrrylHumid Noon: SunnylHumid PM: SunnylHumid <br /> Temperature: 8:00 All,ll 66 Noon: 88 4PM: 85 <br /> PERSONNEL COUNT Spec. Contractor Trade Workforce <br /> Sect. Foreman Journeymen Helper Total- <br /> General <br /> Contractor: DAgostino 1 Job Supt. <br /> Masonry <br /> Subcontractors: <br /> J.J. Enterprises 2 <br /> Boston Contract Drilling <br /> TOTAL _781 <br /> Notes: Submersible pump is continuing to pump water out from recessed floor area, lower level. <br /> Boston Contract core drilled a total of 8 holes in the lower level, north foundation <br /> wall as follows: ELECTRIC DOOM: 2-4"diameter holes.,4- "diameter boles-the <br /> western most of the "diameter holes was made through ars existing masonry infill <br /> panel which appears to have been dislodged at its perimeter due to the core drilling <br /> action. MECHANICAL ROOM: 2-8"diameter holes. <br /> Demolition crew removed plaster and wire lath in both the director"s office and leisure <br /> area on the 1st level, thea began removing both cast from and copper utility lines <br /> In the new storage area, lower level. <br /> General Contractor tools delivery of grit heaters, concrete masonry units, face brick- <br /> soaps, Dur-o-wall ladder type masonry wall reinforcing., " THK styrofoam bl eboard <br /> rigid insulation-Portland cement type 11, lime and clean sant!. Mason spent play setting <br /> p work area and prepping openings in existing CMU bearing wall near selectmen <br /> meeting rooms area. <br /> Maintenance custodian expressed concern re:the width of Moor#L19. 1s door opening <br /> to be ide enough to allover both riding ra wer and grow blower thru to storage area? <br /> Number Key to InspectionNotes: <br /> 1.Work performed by General Contractor 10.Site meeting participants and discussion <br /> 2.Work performed by Subcontrators 11.Variations from plans and specs.P instigator, action , <br /> .Work items or extra started taken,contrs.seeking compen.,item,labor and <br /> .Work items or extra completed materials <br /> a.Potential or encountered delays 12.Description of job incidents and remarks <br /> .Serious accidents 13.Material and equipment for installation received, <br /> 7.Visitors and reasons compliance to specs. <br /> 6.Testing or inspection 14.Work not meeting specifications <br /> . Equipment on site 15. Items in 14 not corrected. <br /> 4tL OF <br /> Copies to: Staff Signed: <br />