Laserfiche WebLink
Project Representative's Daily Report Page t of <br /> Report No. 66 <br /> Date: 10111196 <br /> Architect: Strekalovsky& Holt, Inc. Day: F <br /> Project: Mashpee Town Mall Contractor 'Aostlno Associates <br /> Superintendent: Len Paoletta <br /> Weather: 8:00 AM Ptly cloudy loon: s nnylbree y PM: Ptly sunny <br /> Temperature: 8:00 AM 45 Ion. 54 4PM: 52 <br /> -1-I I I_Pl.q•_ .giliLY <br /> PERSONNEL COUNT Spec. Contractor Trade Workforce <br /> Sect. Foreman Journeymen Helpers Total <br /> 1 I 1 I.■ I_IlYY.i� .14.i .-.iii <br /> General <br /> Contractor: <br /> 'Agostino 1 lob Supt t <br /> Masonry <br /> Subcontractors: <br /> TOTAL <br /> Dotes: Writer conferred with Proj.Arch. Jeanine Delongchamp re: job progress. Concern <br /> was again expressed over the size and span of recently installed metal stuck, <br /> and the fact that they have not been braced, nor has any allowance been built <br /> in for deflection concerns re: the existing and new(wood trusses) bldg.struct. <br /> Ms. Delongchamp instructed the writer to deliver to the Job suet. a copy of the <br /> specified metal stud manufacturer's publication on limiting heights. Accompanying <br /> this was a sketch detail showing how the stud system should be secured to the <br /> underside of structure. The above was accompanied by a letter of transmittal <br /> which furth rrequests a submittal. Copies of the above are made a part of this <br /> report. Upon arrival at the job site, the Writer was greeted by the Bldg Insp., Mr. <br /> Wm. Hauck, who reviewed two pieces of correspondence with the writer that <br /> address Mr. Hauck'sconcems re: recent work efforts on site. The writer did remark <br /> to Mr. Hauck that Strekalovsky&Hoit have been and are addressing all concerns. <br /> The correspondence dated/0110196 and 10/11196 are also made a part of this <br /> report and were reviewed by Ms. Delongchamp. In closing out the afternoon <br /> observations were made of 3 cement masons, In the process of troweling the <br /> recessed area of the lower floor. Both the gest entrance area of the new main <br /> lobby and the 2nd floor landing at stair#2 have been poured. None of the new <br /> metal sural work in the north wings has been braced as of the end of this work day. <br /> Dumber Key to Inspection dotes: <br /> 1.Work performed by General Contractor 10.Site meeting participants and discussion � <br /> .Work performed by Subcontractors 11.Variations from plans and specs., instigator,action <br /> I Work items or extra started taken,contrs.seeking compen., item, labor and <br /> 4.Work items or extra completed materials <br /> .Potential or encountered delays 12.Description of job incidents and remarks <br /> 6.Serious accidents 13.Material and equipment for installation received, <br /> 7.Visitors and reasons compliance to specs. <br /> .Testing or inspection 1 .boric not meeting specifications <br /> . Equipment on site 15.Items in 14 not corrected. <br /> Copies to: Staff Signed: 4 <br />