uunxts - 1 <br /> Fagreers <br /> — Intense Designers <br /> NAPoemSymmes Maini and McKee Associates,Inc. <br /> MEMORANDUM <br /> To: Joel Sealy Date: 10-05-94 <br /> From: Ed Dalton Project No.: 94023 <br /> Project Mashpee High School <br /> Re: Expansion of Air Conditioning System <br /> Distribution: LSM, RG, JMC, (MF) <br /> The intent of this memo is to identify the requirementsuirements for expansion of the air conditioning system <br /> from the present design. The following items are required to expand the air conditioning throughout the <br /> building: <br /> 1. Present chiller and cooling tower are sized for the indicated air conditioned spaces. The future <br /> expansion would require an additional chiller and cooling tower. The present cooling tower would <br /> be replaced with a tower at the capacity required or a additional unit would be purchased, either <br /> scenario the cooling tower would be placed on the roof and the new chiller would be located in the <br /> existing cooling tower space. New transfer pumps would be required between chiller and the <br /> cooling tower. New controls and modification of the existing controls, piping would be required. <br /> 2. The pumps for the chilled water would be replaced. The chilled water supply and return lines to <br /> remain with new tap for equipment connection. <br /> 3. Classroom unit ventilators are selected based on heating only, two pipe system. For future cooling, <br /> the units ventilators would require adding a cooling coil, piping the chilled water to the individual <br /> units, valves and modifications to the present control programs. <br /> 4. Air handling presently for heating and ventilation will be selected on heating/cooling models (blank <br /> section for cooling coil &drain pan) so future expansion (adding a cooling coil) to the units would <br /> only require piping, valves, cooling coil and modifications to the present controls. <br /> i 5. Gas fired units would require installing a duct mounted cooling coil with drip pan, piping, valves, <br /> modification to the ductwork and the present controls. <br /> 6. Present primary and secondary electric services are based on a 183,000 s.f. school with partial air- <br /> conditioning and a future pool building. The expansion of the air-conditioning system to cover the <br /> entire building would increase the size of the primary and secondary services. <br /> 7. The schools primary service presently requires a concrete pad for a 2,000 KVA pad-mounted <br /> transformer which would have to be upgraded to accommodate a 2,500 KVA pad-mounted <br /> transformer. <br /> 1000 Massachusetts Avenue Cambridge Minneapolis Young Quinlan Building 81 South Xinth Street. <br /> Suite 330 <br /> com6ridge.Massachusetts 0 1 1 3 8 – Minneapolis.Minnesota S S 4 0 2 <br /> 617 .547 .5400 Fav : 354 .5158 612 .33'2 .3654 F a x :3 3 2 .3 6 2 6 <br />