Jim said once the CPM is accepted , if the Contractor falls more <br /> than 10% behind , the specs say the Committee can tell the <br /> contractor what to do to catch up . Peter said this CPM becomes <br /> part of the contract' <br /> Yes it does . <br /> Peter said , if the contractor falls behind , he has to catch up at <br /> his expense? <br /> Yes he does . <br /> Paul said it is important to agree with all these line items now , <br /> so they have that leverage when he is falling behind . <br /> Peter asked if the schedule is showing time to move into the <br /> building^ <br /> Joel explained some categories need to be added , FF&E move in , <br /> end testing , for example . Stone must add those to the CPM. <br /> Paul said he feels the contractor is still slipping from the <br /> schedule . <br /> Jim said they have placed an average of 138 feet of footing per <br /> day. 2 weeks ago they said they would be doing 250 £t per day. <br /> Paul would like SMMA to send a letter to Stone notifying them the <br /> Committee feels they are falling behind schedule . He wants to be <br /> on record that the Committee knows they are falling behind . <br /> FF & E <br /> Joel presented a letter to the Committee from Ed Frenette <br /> regarding the technology consultant . SMMA is prepared to <br /> recommend CCR for the final phase of technology consulting . <br /> Paul explained he received a fax from John Brooks,.( as did SMMA <br /> and Dr . DeMoura) . Mr Brooks felt there were at a disadvantage , <br /> felt SMMA was against them and certain figures in the town of <br /> Mashpee were against him. Paul said the letter sounded hostile . <br /> He felt the Committee told him up front they wouldn' t have <br /> invited him if they were not serious . <br /> Paul said the Committee can accept the recommendation of CCR or <br /> ask SMMA to invite someone else . The field is rather new and he <br /> knows of only 1 other firm to possibly invite and he is not sure <br /> they could do the entire job . <br /> Janice said CCR was really enhanced by hooking up with MEC . <br /> Paul agreed. Before the meeting , he had concerns about CCR. He <br /> was impressed with them after the interviews , especially with <br /> Carol of MEC . Paul said Ed Frenette also now feels good about <br /> CCR. They are trying to build a reputation in this market , they <br /> are hungary. <br /> Steve said MEC has been around for awhile and during the last few <br /> years they have specialized in education training/software . He <br /> thinks the Committee has the best combination ( CCR and MEC ) that <br /> exists now. <br /> Janice said she is concerned about the furniture timeline . The <br /> 2 <br />