My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
1996-HIGH SCHOOL BUILDING COMMITTEE
TownOfMashpee
>
Town Clerk
>
Minutes
>
SCHOOL COMMITTEE
>
HIGH SCHOOL BUILDING
>
1990-1999
>
1996
>
1996-HIGH SCHOOL BUILDING COMMITTEE
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
12/1/2016 7:16:49 PM
Creation date
11/17/2016 3:31:01 PM
Metadata
Fields
Template:
Mashpee_Meeting Documents
Board
SCHOOL
Meeting Document Type
Minutes
Meeting Date
12/31/1996
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
211
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
MASHPEE HIGH SCHOOL BUILDING COMMITTEE MINUTES <br /> TUESDAY, MAY 28, 1996 <br /> HIGH SCHOOL SITE <br /> Present: Bill Martiros , Merry Sue Ahlgren, Joe Polito , Paul <br /> Griffin, Steve Greelish <br /> Ian Aitchison, Tom Wren, Jim Byrne, Joel Seeley, John Williams, <br /> Dr. DeMoura, Greg Taylor <br /> Meeting convened at 4 : 04 p.m. <br /> MINUTES <br /> ** Merry Sue made a motion to approve the minutes of May 14 . <br /> Joe seconded the motion. All members were in favor 5-0.** <br /> CONSTRUCTION PROGRESS <br /> Last Friday, Paul attended the weekly morning meeting with Stone <br /> and SMMA. They reviewed each division of the project ; <br /> - drywall, is in good shape . <br /> - ceilings, are a little behind but coming around. <br /> - bricklayer is stalled in some areas . He started 2 smaller crews <br /> to do clean up work. <br /> - block work: they just started this morning on stairs 1 & 2 . <br /> - stairs near the library should be here any day. <br /> - pipe in library, Stone was given a directive to move it. They <br /> gave a directive to the sub to move it within 48 hours . <br /> - windows, are making good headway. The building should be <br /> totally tight within 2 weeks . <br /> - elevator, machinery is in but it is not operating yet. <br /> - heating, expect it on within the next 10 days . <br /> - fans on roof are not on yet ( for de-humidification) , expected <br /> on Friday. <br /> Stone has decided to finish the upstairs first and then work <br /> down, it is less humid upstairs because it is not on slab. <br /> - gym, hardwood floors will not be taken off of the truck until a <br /> moisture check has been done on them first . They will then <br /> acclimate the wood to that area. <br /> - Site work, is coming along well , they are now happy with <br /> Lawrence Lynch' s pace. <br /> Paul explained that July 1 is now the estimated start up date for <br /> the sewage treatment plant, not June 1 . The pumps being used are <br /> Swedish and only available there and they are having trouble <br /> getting them out of the country. Paul recommended they get a <br /> temporary pump to get the plant going. DEP will not be called to <br /> test until there has been flow for 30 days. <br /> Jim added there are still some submittals missing. <br /> Paul said David Patrick and Alan Scott are going to work on it <br /> and speak with our engineers to get an appointment with DEP to <br /> discuss the situation. <br /> Steve said because we are asking DEP to permit a new technology, <br /> they will be a little more involved. We should expect they will <br /> 1 <br />
The URL can be used to link to this page
Your browser does not support the video tag.