My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
02/25/2000 FIRE STATION BUILDING COMMITTEE Minutes
>
02/25/2000 FIRE STATION BUILDING COMMITTEE Minutes
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
4/27/2018 5:04:42 PM
Creation date
4/27/2018 2:22:43 PM
Metadata
Fields
Template:
Mashpee_Meeting Documents
Board
FIRE STATION BUILDING COMMITTEE
Meeting Document Type
Minutes
Meeting Date
02/25/2000
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
12
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Show annotations
View images
View plain text
i <br /> Fire Station Building Committee <br /> Minutes <br /> February 2 ,2000 <br /> 1 . Tentative Construction Schedule: <br /> Tentative start date: April 1, 2000—Ten-month construction schedule. <br /> The permit application with stamped plans and specifications is expected <br /> to be forwarded to the Building Inspector's Office on 2/28/00. <br /> As with normal procedures, work will not proceed if there is a code <br /> violation or critical construction defect until the issue has been corrected. <br /> The Architect indicated that he would be on site.weekly or on a biweekly <br /> ly <br /> basis in the early stages of the project as deemed necessary. <br /> 11. Critical Work Seguencing&Phasing: <br /> The Architect requested to be notified 48 hours in advance to ti <br /> schedule Project Engineers to address agenda items pertaining <br /> to their area of expertise. <br /> To substantial completion dates are considered for the project to rale <br /> the new addition operational. Upon first substantial completion, the <br /> Owner's insurance assumes responsibility for wort , with the exception of <br /> punch list items. The final acceptance of the project will occur after the <br /> second date of substantial completion in phase Il. <br /> The moving of Fire Department staff was discussed. <br /> 12. DesigLiation of Responsible Personnel Project Team Direagy, Chai of <br /> Command and Communication: <br /> Standen Contracting Company distributed an organizational project chart. <br /> The Project Manager is John Marshall. Jerald Loranger is the noted <br /> Superintendent. His resume will be forwarded to the Architect and <br /> Fire Station Building Committee. <br /> The Architect recommended that 1 pasty assume responsibilities to <br /> employ a testing laboratory. It is typically the Owner's responsibility. <br /> (Steel—Owner : Concrete--Contractor) <br /> Chain of Command: Fire Department—Fire Chief l eputy fire Chief <br /> Project Superintendent Architect <br />
The URL can be used to link to this page
Your browser does not support the video tag.