Laserfiche WebLink
Town of Mashpee Sewer Commission <br /> t <br /> 16 Great Neck Road North <br /> Mashpee, MA 02649 <br /> o Contract 5: Work near Town Hall began the week starting on the 15th. <br /> o Contracts 4, 5, 6: Linear work had not fully started; current activity included <br /> installation of green stakes marking proposed lateral locations for residences. <br /> Additional contractors were expected to start soon. <br /> Traffic Notifications and Project Tracking Tools <br /> Mr. Drainville reviewed how traffic and construction notifications appear on the Town/Sewer <br /> Commission website: <br /> • Residents can use the Sewer Project Status page and open the construction progress <br /> schedules to view a 3-week look-ahead of work and traffic impacts by contract. <br /> • The Phase 2 project was moved to the top of the list for easier access. <br /> • The schedule was described as color-coded by contract so residents can identify which <br /> work applies to them more quickly. <br /> GIS System and Green Stake Process <br /> Mr. Drainville stated the GIS system is active and is being populated by resident representatives: <br /> • Resident representatives will photograph green stake locations for each property and <br /> upload those photos to the GIS system. <br /> • The GIS tool is intended to help residents who are away for extended periods see where <br /> the stake is placed relative to the home and begin discussions early if changes are <br /> requested. <br /> • The GIS system will be available through a Town webpage hotlink and searchable by <br /> property address. <br /> Green stake placement details discussed: <br /> • Typically one stake is placed, based on a straight-line approach to the road. <br /> • In certain cases (such as driveways or obstacles), an offset stake may be used and noted; <br /> an offset may be marked in pink. <br /> • If residents raise concerns, staff can review plans with them to explain expected routing <br /> and placement. <br /> Notifications: <br /> • Residents were told two notifications are being provided: a mailed letter and a hand- <br /> delivered door hanger. <br /> • The notice includes contact information for both the engineer and the contractor. <br /> Planned Public Update Sessions <br /> Mr. Drainville said he and Mr. Meader discussed starting regular public update meetings, <br /> potentially quarterly, held at night. Topics would be driven by public questions and could include <br /> technical issues such as groundwater recharge mounding. Mr. Meader stated the intent is to hold <br /> sessions based on the issues and questions coming in at the time and to treat it as a public- <br /> focused meeting. <br /> Mashpee/Wakeby Subsurface/Collection System Permitting Status <br /> Mr. Drainville gave a brief update on the Mashpee/Wakeby subsurface and collection system <br /> work: <br /> The project is in the permitting phase. <br />