Mashpee High School Project Management CCG12Q4Mn7M /ANDREW CHARTWELL 8 CO <br /> 6.0 Construction Schedule and Time Control <br /> 6.1 Construction Schedule: see comment as 5.1 above. <br /> 6.2 'Primavera' is the Contractor's intended CPM software. <br /> 6.3 Interim submissions and written reports of matters likely to have an impact on the <br /> Critical Path(s) are to be sought from the Contractor in the event of a slippage to <br /> Schedule arising. <br /> 7.0 Site Meetings <br /> 7.1 Forthnightly Project progress coordination meetings will be held with the Contractor. <br /> ACC/COW will attend. A suitable day is to be agreed with the Contractor. SMMA will <br /> prepare and distribute the minutes of the said meetings. ACC will keep independent <br /> notes and will convey any additional comments to SMMA upon receipt of the draft <br /> minutes. The aim is that the second (end-of the-month) meeting will be timed to <br /> coincide with the interim payment requisition and that it will be held prior to the <br /> monthly Building Committee meeting. <br /> 7.2 Coordination meetings between the Contractor and his subcontractors will be held <br /> on a weekly basis. Minutes of these meetings will be prepared and distributed by <br /> the Contractor with a copy to SMMA and ACC. Ordinarily, SMMA will not attend this <br /> meeting series. The aim is that the COW will attend. <br /> 7.3 SMMA confirmed that the Contractor will be attending the meetings of the Building <br /> Committee. <br /> 8.0 Hours of Work at Site <br /> 8.1 ACC sought clarification on the policy to be adopted in the event that the Contractor <br /> seeks overtime, double-shift or week-end working, particularly as it would impact <br /> the workload of the COW. The Contractor's normal working hours should be sought <br /> as soon as possible. SMMA replied that no provision exists under the Contract for <br /> the recovery of additional supervision or observation costs from the Contractor <br /> (through the Owner). ACC considered that the matter required further study. <br /> 9.0 Site Safety and First Aid <br /> 9.1 SMMA confirmed that all aspects relating to site safety, including emergency <br /> procedures, are a matter for the Contractor. <br /> Sheet 4 of 6 Administration of the Project May 4, 1995 <br />