Project Representative's Daily Report Page t of 7 <br /> Report N . 53 <br /> Date: 9116196 <br /> Architect: Strekalo sky&Hoit, Inc. Davy: M <br /> Project: Mashpee Town Hall Contractor D"Agostina Associates <br /> Superintendent: Leri Paoletta <br /> Weather: 8:00 AM Cloudy Noon: Partly Cloudy PVI: Pt CldlShwrs <br /> Temperature: 8:00 AM 60 Noon: 74 4PM: 71 <br /> PERSONNEL CANT Spec. Contractor Trade Workforce <br /> Sect. Foreman Journeymen Helper Total <br /> General <br /> Contractor <br /> D"Aggostino 7 Job Supt. <br /> Masonry 1 2 3 <br /> Subcontractors: <br /> Bonn's Excavating 7 2 <br /> Riordan Electric 7 2 3 <br /> TOTAL 177 <br /> Notes: Carpenters are installing the remainder of trusses throughout the 1st level overhead. <br /> 73 trusses remain to be installed. Carpenters have strapped the bottom charm of trusses <br /> with 7x stack and are at present using the corridor wails as bearing. <br /> Masons are prepping openings along corridor#2-North wing counter opening at <br /> Treasurer's office. Excavator has backfilled and compacted in 6"lifts, slab areas at <br /> both the east and west entrances in anticipation of new slab work. The electricians <br /> installed hangers in the north wing. Cable trays have been installed incorrid r overhead, <br /> south wing, 7st floor. PVC conduit run stub-ups to chiller pad, north enol of site have als <br /> NOTE: NO EITUMASTIC C A TING HA S BEEN APPLIED TO ROOF TO TEMP, <br /> 1 EA THE1 1 G GF ENCLOSURE FOR EL E TRICA L POWER ER PAI EL . STEEL IS <br /> NOT ON SITE.. TRUCK BROKE DOWN. <br /> Number Key to Insp cMonNotes: <br /> 1.Work performed by General Contractor 10.Site meeting participants and discussion <br /> .Work performed by Subcontractors 11.Variations from plans and specs.,instigator,action <br /> .Work items or extra started taken,contrs.seeping compen., item, labor and <br /> 4.Nark items or extra completed materials <br /> . Potential or encountered delays 12.Description of job incidents and remarks <br /> . Serious accidents 13.Material and equipment for installation received, <br /> .Visitors and reasons compliance to specs. <br /> 8.Testing or inspection 14.Work not meeting specifications <br /> . Equipment on site 15.Items in 14 not corrected. <br /> Copies to: Staff Sig <br />